November 2, 2021 8:00 AM

White Rock Lake Trail Construction

The White Rock Lake Trail is undergoing reconstruction from Nov 2021 to Summer 2022. The trail will be widened to 12' from the Bath House to Winfrey Point. To be more accommodating for trail users, the trail construction work will occur in two phases:
• Phase One is from Northcliff Dr. to Dixon Branch from November 2021 to February 2022 and the trail will be closed for construction during this time.
• Phase Two is from Dixon Branch to Winfrey Point from February 2022 to July 2022 and the trail will be closed for construction during this time.
During construction on both phases, park users should expect signs posted indicating the trail is closed and some areas fenced off for staging areas for construction equipment at designated locations in the park. Trail traffic will be re-routed onto E. Lawther Rd. when the trail is closed. Thank you for your patience during this time.

Questions and Concerns can be directed to the Project Manager at: Mehul Pithadia at: mehul.pithadia@dallascityhall.com or call 214-670-1527